PROVO CITY WASTEWATER TREATMENT PLANT EXPANSION PUBLIC NOTICE OF FINDING OF NO SIGNIFICANT IMPACT
Notice Tags
Water Quality
Notice Type(s)
Notice
Event Start Date & Time
May 19, 2025 04:00 PM
Event End Date & Time
June 18, 2025 05:00 PM
Description/Agenda
PROVO CITY WASTEWATER TREATMENT PLANT EXPANSION PUBLIC NOTICE OF FINDING OF NO SIGNIFICANT IMPACT
TO ALL INTERESTED GOVERNMENTAL AGENCIES AND PUBLIC GROUPS
The Division of Water Quality (DWQ), Utah Department of Environmental Quality (DEQ), herewith publishes a Finding of No Significant Impact (FONSI) for the Provo Wastewater Treatment Plant Expansion located in Provo, Utah County, Utah. An Environmental Assessment (EA) was developed to examine potential environmental impacts associated with the project.
As required by guidelines for preparing Environmental Impact Statements (EIS), an environmental review was performed on the proposed State of Utah, DWQ action below:
PROJECT INFORMATION
PROJECT NAME: Provo Wastewater Treatment Plant Expansion
MAILING ADDRESS: 1377 S 350 E
Provo, UT 84606
PROJECT LOCATION: 1685 S 350 E
Provo, UT 84606
WATERCOURSES: Mill Race
ESTIMATED PROJECT COST: $26,750,000
PROJECT NUMBER: SRF 278
FEDERAL/STATE/LOCAL SHARE: $7,000,000 from Utah Water Quality
Board (Board) and $19,750,000 in local contribution.
PERMIT INFORMATION
FACILITY NAME: Provo City Water Reclamation Facility
MAILING ADDRESS: 1377 South 350 East
Provo, UT 84606
TELEPHONE NUMBER: (801) 852-6780
PERMITTEE NAME: Provo City
PERMIT TYPE: Utah Pollutant Discharge Elimination System
PERMITTEE NO.: UT0021717
PERMITTEE NAME: Provo City
PERMIT TYPE: Biosolids Permit
PERMIT NO.: UTL021717
BACKGROUND
Provo City began major upgrades to their wastewater treatment plant in 2020, but due to construction cost increases a portion of the project was delayed. This project will implement the third of three membrane bioreactors to improve the facility's nutrient management. The discharge from this facility flows into Mill Race which ultimately discharges to Provo Bay. There will not be an increase in impacts from their current permit and effluent limitations. Therefore, an Antidegradation Review (ADR) was not necessary to complete for this project. However, during 2020 an ADR was conducted for the selection of the MBR treatment process.
The Board approved funding for this project by authorizing a $4,500,000 loan at 0.75% over 20 years and $2,500,000 as principal forgiveness. The rest of the balance of the project will be made up using local contribution of $19,750,000.
The proposed project will occur on a construction site which has previously been disturbed. No wetland impacts are anticipated for the project. The proposed project would not modify or eliminate any recreational open space and would be unlikely to impact any agricultural lands. The project should not cause any increased impacts to air quality. The additional discharge should not significantly alter stream flow conditions or result in stream bank modifications. An EA was prepared by Water Works Engineers as part of Provo City's Capital Facilities Plan. The EA evaluated the potential environmental effects and consequences of the proposed addition.
ANNOUNCEMENT
This notice announces the availability of the EA which is included in the 2020 Capital Facilities Plan1, the Budget and Phasing Plan2, and the Environmental Review3 for public review and comment.
Based on the information in the EA, as summarized here, DWQ determines that the proposed action will not significantly impact water quality. Additionally, the review process did not indicate significant environmental impacts would result from the proposed action. The preliminary decision is to not prepare an EIS and the DWQ is issuing a FONSI for the proposed action. This action is taken on the basis of a careful review of the Capital Facilities Plan, environmental information documents, and other supporting information. These documents are available for public review online on the DWQ's Public Notice Webpage.
Comments supporting or disagreeing with this decision may be submitted for consideration by DWQ. After evaluating the comments received, DWQ will make a final decision.
No administrative action will be taken on the project for at least thirty (30) calendar days while advertising the FONSI, Capital Facilities Plan, and EA.
Questions or comments may be directed to George Meados via email at wqcomments@utah.gov or if necessary via telephone at (385) 232-1247. (Note: Please Include 'Provo Wastewater Treatment Plant FONSI' in the subject line of any email)