Description/Agenda
Summit County Service Area #3
Rotomill Millings Surfacing Project
Description of Work
A. Coordinate work schedule with the Engineer to obtain, spread, and compact the
rotomill millings at the locations shown in the project map, or as directed by the
Engineer.
B. Rotomill tailings will be placed on the roadways as directed by the engineer from a
di!erent project shown on the project map (next page).
C. If miillings are not placed on the roadways, obtain the millings that will be stockpiled
at a few potential locations shown on the project map.
D. Spread millings uniformly in 3 inch lifts on the routes shown in the project map.
E. Prepare, spread and compact millings such that final surface is graded for adequate
surface water runo!.
F. Compact the entire surface of each lift of millings with at least 4 to 6 passes of a
vibratory roller as verified by the engineer.
Proposals are due June 3rd, 2025 at 4:00 PM.