Center Street Overpass Statement of Qualifications (SOQ) Information Sheet
August 17, 2018
Vineyard City, Utah (Owner) is prequalifying bidders for a project in Vineyard. The intent
of the prequalification process is to provide the Owner with a high degree of confidence
and increase the likelihood that the low bidder will be an experienced contractor who can
successfully complete the project. The prequalification process will allow the City to
select experienced contractors to bid on the project who have demonstrated history of
delivering high-quality products and successfully completed similar projects on time and
within budget.
Submittal of the Statement of Qualifications (SOQ) does not guarantee an opportunity to
bid on the Project. Only contractors selected through this prequalification process will be
allowed to bid on the project.
DESCRIPTION OF WORK:
Contractors will be prequalified for the following project as described below. This
description is preliminary and is subject to change.
Center Street Overpass
This project consists of constructing a 2-lane overpass bridge from the limits of
Mill Road to Vineyard Road over the existing UPRR/UTA railroad tracks.
Construction will consist of approximately 110,000 CY of backfill, surcharge,
construction of 170 LF concrete span and 1,800 tons of hot mix asphalt with its
accompanying roadway structural section. The project will also include complete,
in place and new traffic signals at the intersections of Center Street/Mill Road and
Center Street/Vineyard Road.
SOQ REQUIREMENTS:
The completed SOQ with supporting documentation must be received on or before 4:00
p.m., local time, on Monday, September 10, 2018. No late submittals will be considered.
Submit the SOQ documents in a sealed envelope labeled 'Vineyard City, Utah Center
Street Overpass SOQ Enclosed' via mail or in person to:
Don Overson, P.E.
125 South Main St.
Vineyard, UT 84058
The SOQ shall be limited to eight (8) 8 1/2' x 11' pages. A one-page cover letter and a
cover sheet may be included, without either counting towards the eight (8) SOQ pages.
Please submit the following information in the SOQ:
Contractor and Subcontractor Information
Please list subcontractors that you propose to team with on the project. A
subcontractor completing 5% or more of the work must be prequalified to work
Notice of Special Accommodations (ADA)
SPECIAL ACCOMMODATION DURING PUBLIC MEETINGS
The Public is invited to participate in all City Council meetings. In compliance with the Americans with Disabilities Act, individuals needing special accommodations during this meeting should notify the Vineyard Recorder, at least 24 hours prior to the meeting by calling (801) 226-1929.
Notice of Electronic or Telephone Participation
POSSIBLE ELECTRONIC OR TELEPHONIC PARTICIPATION
One or more members of the Vineyard City Council may participate electronically or telephonically.
EXECUTIVE SESSION
The City Council may vote to go into Executive Session pursuant to Utah State Code 52-4-204 and 52-4-205.