GRANTSVILLE WASTEWATER TREATMENT PLANT UPGRADE PUBLIC NOTICE OF FINDING OF NO SIGNIFICANT IMPACT
Notice Type(s)
Notice
Event Start Date & Time
December 24, 2025 03:50 PM
Event End Date & Time
January 23, 2025 05:00 PM
Description/Agenda
State of Utah
SPENCER J. COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
Department of Environmental Quality
Tim Davis
Executive Director
DIVISION OF WATER QUALITY
John K. Mackey, P.E. Director
December 24, 2025
GRANTSVILLE WASTEWATER TREATMENT PLANT UPGRADE PUBLIC NOTICE OF FINDING OF NO SIGNIFICANT IMPACT
TO ALL INTERESTED GOVERNMENTAL AGENCIES AND PUBLIC GROUPS
The Division of Water Quality (DWQ), Utah Department of Environmental Quality (DEQ), herewith publishes a Finding of No Significant Impact (FONSI) for the Grantsville Wastewater Treatment Plant Upgrade located in Grantsville, Tooele County, Utah. An Environmental Assessment (EA) was developed to examine potential environmental impacts associated with the project.
As required by guidelines for preparing Environmental Impact Statements (EIS), an environmental review was performed on the proposed State of Utah, DWQ action below:
PROJECT INFORMATION
PROJECT NAME: Grantsville Wastewater Treatment Plant Upgrade
MAILING ADDRESS: 429 East Main Street
Grantsville, UT 84029
PROJECT LOCATION: 630 North Race Street
Grantsville, UT 84029
WATERCOURSES: Blue Lakes
ESTIMATED PROJECT COST: $26,750,000
PROJECT NUMBER: SRF 283
FEDERAL/STATE/LOCAL SHARE: $16,000,000 from Utah Water Quality
Board (Board) and $18,633,000 in local contribution.
PERMIT INFORMATION
FACILITY NAME: Grantsville City Water Reclamation Facility
MAILING ADDRESS: 429 East Main Street
Grantsville, UT 84029
TELEPHONE NUMBER: (435) 884-3411
PERMITTEE NAME: Grantsville City
PERMIT TYPE: Utah Pollutant Discharge Elimination System
PERMITTEE NO.: UT0021130
PERMITTEE NAME: Grantsville City
PERMIT TYPE: Biosolids Permit
PERMIT NO.: UTL021130
BACKGROUND
Grantsville City is upgrading their wastewater treatment plant to treat up to 3 million gallons per day to meet current and future needs. This project will consist of a fine bubble diffuser aeration system, new headworks building, biological nutrient removal basins, secondary clarifiers, and tertiary filtration within the current property line. The discharge location will remain the same discharging into a ditch that connects to Blue Lakes. A Level II Antidegradation Review was completed because this project will result in an increase in flow.
The Board approved funding for this project by authorizing a $16,000,000 loan at 0.75% over 30 years. The rest of the balance of the project will be made up using local contribution of $18,633,000.
The proposed project will occur on a construction site which has previously been disturbed. No wetland impacts are anticipated for the project. The proposed project would not modify or eliminate any recreational open space and would be unlikely to impact any agricultural lands. The project should not cause any increased impacts to air quality. The additional discharge should not significantly alter stream flow conditions or result in stream bank modifications. An EA was prepared by Jones & DeMille Engineering. The EA evaluated the potential environmental effects and consequences of the proposed addition.
ANNOUNCEMENT
This notice announces the availability of the EA and the Wastewater Treatment Plant Study for public review and comment.
Based on the information in the EA, as summarized here, DWQ determines that the proposed action will not significantly impact water quality. Additionally, the review process did not indicate significant environmental impacts would result from the proposed action. The preliminary decision is to not prepare an EIS and the DWQ is issuing a FONSI for the proposed action. This action is taken on the basis of a careful review of the Wastewater Treatment Plant Study, environmental information documents, and other supporting information. These documents are available for public review online on the DWQ's Public Notice Webpage.
Comments supporting or disagreeing with this decision may be submitted for consideration by DWQ. After evaluating the comments received, DWQ will make a final decision.
No administrative action will be taken on the project for at least thirty (30) calendar days while advertising the FONSI, Wastewater Treatment Plant Study, and EA.
Questions or comments may be directed to George Meados via email at wqcomments@utah.gov or if necessary via telephone at (385) 232-1247. (Note: Please Include 'Provo Wastewater Treatment Plant FONSI' in the subject line of any email)
John K. Mackey
P.E. Executive Secretary, Utah Water Quality Board
Notice of Special Accommodations (ADA)
In compliance with the Americans with Disabilities Act, individuals needing special accommodations (including auxiliary communicative aids and services) during this meeting should notify Emily Canton at 801-536-4342.